Nandipur power plant again resumes power generation

PakistanNandipur power plant again resumes power generation

ISLAMABAD, Pakistan: The much delayed 525 MW Nandipur Power Plant which went out of order soon after its inauguration in May this year has again resumed its generation by supplying 430 MW to the national grid system.

Official sources told APP here Tuesday, the power plant was being run on furnace oil. The plant would generate 525 MW after being run on gas and the conversion would take around five months.

The sources said that RLNG would also be available for Nandipur shortly resulting in generation of much cheaper electricity from the plant.

The project was conceived to be run on natural gas but it was decided to make it a dual fuel plant as financiers were not ready to invest in a single fuel plant, they said.

The sources said that the project was conceived and approved during military dictator Gen (R) Pervez Musharraf regime. However, during the tenure of the previous federal government, the project was delayed for about four years resulting in surge in its cost from $329 million to $847 million.

They said that despite so many constraints, the project was completed within its estimated approved PC-1 cost of Rs 58 billion.

The sources said that plant successfully completed test run but later was shut down due to cancellation of Operation and Maintenance agreement with a Malaysian firm.

They said that the Nandipur power plant was the second most efficient thermal power plant after 747 MW Guddu power plant.

The sources said that the National Electric Power Regulatory Authority (NEPRA) had approved Rs 11.3 per unit tariff for the Nandipur Power Project for generation of electricity from furnace oil.

But GENCO-III has already submitted request with Nepra to increase the already decided tariff as some costs were not considered by the authority while determining its tariff.

It is pertinent to mention here that keeping in view the energy crisis in the country, soon after coming into power, the incumbent government started work on the project and completed it within its stipulated time period.

Source: APP

Mati
Mati
Mati-Ullah is the Online Editor For DND. He is the real man to handle the team around the Country and get news from them and provide to you instantly.

Must read

Recent News

Dr. Attia Anwar

Good and nourishing food, the pillar for wellbeing

0
By Dr. Attia AnwerThe food we eat has a role in our physical and mental health. First of all physical health and mental...

Lt. Gen. S M Kamr-ul-Hassan of Bangladesh met COAS Gen Asim Munir and CJCSC...

0
Rawalpindi, Pakistan: Lieutenant General S M Kamr-ul-Hassan, Principal Staff Officer (PSO) of the Armed Forces Division of Bangladesh, is visiting Pakistan and met with...
Remembering Operation Zarb-e-Azb--- An action to clean terrorism from Pakistan

Pakistan’s Security Situation 2024: 444 terrorist attacks against security forces, resulting in 685 personnel...

0
Monitoring Desk: The year 2024 has proven to be the deadliest year in Pakistan in terms of security forces and civilian casualties in the...
Pakistani students participate in Harvard Model United Nations Dubai 2025

Pakistani students participate in Harvard Model United Nations Dubai 2025

0
Press ReleaseDubai, UAE: Harvard University’s International Relations Council (IRC), in collaboration with WorldView Education, organized the Harvard Model United Nations (HMUN) Dubai 2025 from...

Indian Visa Bumper Sale for Afghans

0
Monitoring Desk: After establishing a strategic partnership, India reopened the "e-Emergency X-Misc Visa" category for Afghans this week in Dubai so both countries can...
Advertisement