CCE approves purchase of additional 100 MW electricity from Iran

Government of PakistanCCE approves purchase of additional 100 MW electricity from Iran

ISLAMABAD, Pakistan:  The Cabinet Committee on Energy (CCE) on Thursday approved purchase of additional 100 MW electricity from Iran and directed the Ministry of Power to make immediate arrangements and to complete the spadework expeditiously.

Chaired by Prime Minister Shahid Khaqan Abbasi, the CCE meeting reviewed progress of transmission line project for Port Qasim, Coal-Fired Power Plants, Neelum-Jhelum project, Hydel Power Projects, Trabela-IV and Golen Gol Hydel Power Project.

Managing Director NTDC informed the meeting that work on all transmission lines has been expedited. Transmission Line to evacuate power from Port Qasim power plant will be completed ahead of scheduled date of October 31, 2017.

Similarly, transmission lines for Neelum-Jehlum and Tarbela-IV will also be completed before the projects start producing electricity.

For Golen Gol HPP, 13MW of electricity will be made available by December 2017. Moreover, in order to provide electricity to all the valleys in Chitral, two projects worth Rs. 5.1 billion have been prepared and PC-1s are under process in the Planning Division.

The Prime Minister directed Ministry of Power to expedite transmission line projects for connecting Makran Division with then national grid on priority basis.

The Prime Minister also directed Ministry of Power and PESCO to expedite approval of PC-1 so that all the village in Chitral can be electrified as soon as possible.

Ministry of Power informed the meeting that Government of Iran was interested in providing 100MW of electricity in addition to existing arrangement for 100 MW which is renewed annually. For the additional 100 MW, transmission line and grid station has to be constructed to meet immediate needs of Makran division especially Gwadar Port and industrial area.

Ministry of Power also informed the meeting that as per the latest projections, Pakistan will have surplus power starting in the year 2017-18. This surplus power will be further augmented during the subsequent years with the addition of new capacity from the Thar Coal as well as upcoming hydel projects.

Additional power will be sufficient to cater for the growing demand for industry as well as domestic consumers.

Source: APP

Mati
Mati
Mati-Ullah is the Online Editor For DND. He is the real man to handle the team around the Country and get news from them and provide to you instantly.

Must read

Recent News

The formation of a Judicial Commission would frustrate the legal process against the culprits of the May 9 incidents

Delayed but Not Denied: Names of 25 persons who are convicted in May 9...

0
Islamabad, Pakistan: After getting approval from the Supreme Court this week, the military courts announced the verdict of the May 9 2023 Mutiny case...

Terrorism in Russia: Central Asian Youth Becoming hired-guns

0
Monitoring Desk: The killing of top Russian General Igor Kirillov along with his assistant confirmed again connections between emerging terrorism and Central Asian republics.This...
Why the Season of US Sanctions starts against Pakistan?

Why did the Season of US Sanctions start against Pakistan?

0
Islamabad, Pakistan: On December 19, 2024, the US again imposed sanctions on Pakistan, and the Foreign Office of Pakistan believes the US decision to...
Mustafa Sayed Appointed as Inaugural Member

BRI’s Green and Low-Carbon Expert Network kicks off with Mustafa Sayed appointed as Inaugural...

0
Beijing, China: The BRI Green and Low-Carbon Expert Network (GLEN) was formally launched in Beijing.The network, supported by the Ministry of Ecology and Environment...

US imposes further sanctions on Pakistan

0
Monitoring Desk: The US has again imposed sanctions on Pakistan for its ballistic missile program claiming that Pakistan's program falls under the proliferation of...
Advertisement